Final Invoice
Teresa,
The site turned out really well. I've had several Diocesan Florida employees mention how nice it looks, along with a church we were speaking to last week. It looks like Ryan has finished tieing up the loose ends he still had on his plate. In June we invoiced you for $5760, which was the work done up until June 25th. At that time the project breakdown was:
Design: 78.4 hours | Building: 25.1 hours | Content Migration: 11.7 hours
Total: 115.2 hours
Cost: $5760
Ryan finished the project below our budgeted hours for the Build process. The final project breakdown is:
Design
105 Budgeted | 78.4 Used
Build
112 Budgeted | 106.3 Used
Content Migration
36 Budgeted | 30.7 Used
The remaining amount to be invoiced is $5010, 100.2 hours (81.20 Build hours + 19 Content hours). I will submit the final portion to our billing department.
Gary Smith
The site turned out really well. I've had several Diocesan Florida employees mention how nice it looks, along with a church we were speaking to last week. It looks like Ryan has finished tieing up the loose ends he still had on his plate. In June we invoiced you for $5760, which was the work done up until June 25th. At that time the project breakdown was:
Design: 78.4 hours | Building: 25.1 hours | Content Migration: 11.7 hours
Total: 115.2 hours
Cost: $5760
Ryan finished the project below our budgeted hours for the Build process. The final project breakdown is:
Design
105 Budgeted | 78.4 Used
Build
112 Budgeted | 106.3 Used
Content Migration
36 Budgeted | 30.7 Used
The remaining amount to be invoiced is $5010, 100.2 hours (81.20 Build hours + 19 Content hours). I will submit the final portion to our billing department.