Good afternoon everyone,

I hope you all have been well.
 
As we progress with your new website, we would like to give you an update on how the progress is going this week. Here are the three main stages of how your website is progressing.
  • Design is 100% complete
  • Development is 45% complete
  • Content Migration is In Queue

If you have any questions please feel free to reach out at any time. 

Thank you!

- Alan Snodgrass
Web Consultant




FROM THE CLIENT Carol Payne, Mary School - Srping Lake, MI Staff
Alan,
Please renew the ability - send us the link - to see the new website - thank you.
TO THE CLIENT Arthur Richardson, Web Project Manager at Diocesan
Hello,

Your site is still being worked on, so we do not feel that the site is ready for you to see. Once your site has been filled with content, our content team will send you the development link.

That being said, here is the design link that you approved: https://xd.adobe.com/view/9d0836d4-a2cf-4ba7-a152-e9d92eee0c2e-c85b/

Let us know if there is anything we can do to help. Happy 4th of July!

Thanks and God bless,

Arthur Richardson