Amy,

This morning Kyle & Mary went over what was left on your site build, in regards to the build process and content. I had mentioned previously that due to some design changes we had ended up using more design hours than were budgeted (we had budgeted 30 and ended up using 39), it looks like Mary was able to gain back a little bit of time in the content migration area. Which will put us close to our initial budgeted cost figure. I know that Kyle has some more items he needs to complete for the build and that Mary has some a little more content to enter on the church side and that content from the school is still coming in. Overall we are looking to be close to that projected amount barring any unforeseen issues. 

Current status:
Design  
Budgeted: 30    Used: 39  

Site Build
Budgeted: 60   Used: 56  

Content Migration
Budgeted: 40   Used: 12