As we progress with your new website, we would like to give you an update on how the progress is going this week. Here are the three main stages of how your website is progressing.
  • Design is 100% complete
  • Build is 35% complete
If you have any questions please feel free to reach out at any time. 

Thank you!

Alan Snodgrass
Consultation Specialist
Phone: 877-923-0777 

FROM THE CLIENT Allie Wing, St. Brigid C & S, Dublin OH Staff
Thanks for the update Alan!

Just checking -- is the build portion currently being worked on, and/or are you in need of anything from me at the moment?

I do a lot of updates to the websites this time of year (new forms, handbooks, etc.) so I am continuing with that, so I just want to make sure the info I continue to update will be transferred when we get to that part of the process. We are not in a rush for launching the new sites (as anything earlier than September would be too early due to the new school year starting off).

Thanks!
Allie
TO THE CLIENT Alan Snodgrass, Diocesan
Good morning Allie,

I checked with Cody and at this point, we are not in need of anything.

If you are just updating forms and handbooks on an existing page, that will be brought over for you.  If you were to create a new page, we would need you to update the approved sitemap with that new information.

Let me know if you have any questions.

Thank you!

- Alan Snodgrass
Web Consultant
877-923-0777
FROM THE CLIENT Allie Wing, St. Brigid C & S, Dublin OH Staff
I am just updating forms and links, so we should be good, thank you!